Development & Schemes
Parameter 4: Gram Panchayat Development Plan (GPDP)
GPDP (Gram Panchayat Development Plan)
GPDP 2024-25
| Planning Year | 2024-25 |
| Activities Planned | 25 works |
| Total Budget | ₹50,00,000 |
| Amount Utilized | ₹45,00,000 (90%) |
| Works Completed | 22 works (88%) |
| Uploaded on eGramSwaraj | Yes ✓ |
| Approval Date | October 2, 2024 (Gram Sabha) |
GPDP 2023-24
| Activities Planned | 20 works |
| Total Budget | ₹42,00,000 |
| Amount Utilized | ₹40,00,000 (95%) |
| Works Completed | 19 works (95%) |
| Uploaded on eGramSwaraj | Yes ✓ |
GPDP 2022-23
| Activities Planned | 18 works |
| Total Budget | ₹38,00,000 |
| Amount Utilized | ₹36,50,000 (96%) |
| Works Completed | 17 works (94%) |
| Uploaded on eGramSwaraj | Yes ✓ |
Convergence of Schemes in GPDP
Major central and state schemes converged in the GPDP:
| Sr. No. | Scheme Name | Converged in GPDP | Works Planned |
|---|---|---|---|
| 1 | MGNREGA (Mahatma Gandhi National Rural Employment Guarantee Act) | Yes ✓ | 8 works |
| 2 | PMAY (Pradhan Mantri Awas Yojana) | Yes ✓ | 15 beneficiaries |
| 3 | JJM (Jal Jeevan Mission) | Yes ✓ | Water connections |
| 4 | SBM (Swachh Bharat Mission) | Yes ✓ | Sanitation works |
| 5 | PMGSY (Pradhan Mantri Gram Sadak Yojana) | Yes ✓ | Road connectivity |
| 6 | 14th Finance Commission Grants | Yes ✓ | Various |
| 7 | 15th Finance Commission Grants | Yes ✓ | Various |
Major Development Works (2024-25)
Infrastructure
Road Construction
CC Road - Village 1 to Village 2
Budget: ₹8,00,000
Status: Completed ✓
Water
Water Supply Scheme
Piped water connections - 50 households
Budget: ₹6,50,000
Status: Ongoing
Sanitation
Community Toilet
Public toilet facility at market area
Budget: ₹4,00,000
Status: Completed ✓
Social
Community Hall Renovation
Repair and modernization
Budget: ₹3,50,000
Status: Completed ✓
Agriculture
Farm Pond Construction
Water conservation - 5 farm ponds
Budget: ₹5,00,000
Status: Completed ✓
Education
School Building Repair
Primary school maintenance
Budget: ₹2,50,000
Status: Completed ✓
Participatory Planning Process
GPDP Preparation Process
- Ward Sabha Meetings: Conducted in all 5 wards (August 2024)
- Needs Assessment: Community needs identified through discussions
- Standing Committee Meetings: Sectoral planning by committees
- Draft GPDP Preparation: Consolidated plan prepared (September 2024)
- Gram Sabha Approval: Plan approved on October 2, 2024
- Upload to eGramSwaraj: Plan uploaded within deadline
- Implementation: Works executed throughout the year
Gram Panchayat Janegaon